Client – CW Fire Protection Service Ltd
Site – Tower 42
Location – London, EC2
Contract Duration – Three separate out of hours visits
Services Supplied:
To carry out six liquid nitrogen pipework freezes for Tower 42, to isolate the pipework for CW Fire Protection Service Ltd maintenance works to take place.
Services Completed Included:
During three separate visits to the site, during out of normal working hours, our highly skilled team of engineers carried out six liquid nitrogen pipework freezes.
Using freeze jackets and liquid nitrogen, our skilled engineers isolated the pipework to allow for CW Fire Protection Service Ltd maintenance work to be carried out.
Once the work was complete, we allowed the pipework freezes to thaw, so that any potential leaks could be found.
We were also required to manufacture three channel brackets that were 3 meters tall and span 2 meters wide and painted with red oxide paint.
The site was cleared off all redundant items and was left clean and tidy.
Result:
Six successful pipe freezes all completed out of normal working hours, within the time required.
~
For further details on IDWe Ltd’s Pipe Freezing Services and to get a quote, please click here.
Get a quote, please call 020 8302 7644 or email: info@idwe.co.uk
Want to keep up to date with IDWe Ltd’s news & projects? Follow us on social media: Facebook, Twitter & LinkedIn.