Location: Piccadilly, London
Value: £60k
Contract Duration: 2 weeks
Our task at Le Meridien Hotel was to replace two Cooling Towers.
With the Cooling Towers located on a roof, we engaged a crane hire company to assist with this process.
This project was carried out in 2 lifts over 2 consecutive weekends.
We managed to place the Cooling Towers in exactly the same positions which ensured that no pipework modifications were required. Once in place, the Cooling Towers were commissioned and left operational as they were replaced.